FDOT's I-95 and Northlake Boulevard interchange job is due to start Friday, Nov. 13. Beeline at Jog Road stays right turns only on weeknights through Nov. 19.

Last checked Nov. 10, 2026. Facts on this page come from the Florida Department of Transportation District 4, its Palm Beach County traffic report for Nov. 6 to Nov. 13 (PDF) and the City of Palm Beach Gardens. This page is updated every week.

The biggest job near Palm Beach Gardens right now is the state’s rebuild of Beeline Highway (State Road 710) on the city’s western edge, which is closing lanes on Beeline, Northlake Boulevard, Jog Road and Florida’s Turnpike. A second state project, at I-95 and Northlake Boulevard, is due to start Friday, Nov. 13; we have the details in our story on the I-95 and Northlake work. For live conditions before you drive, check FL511 or call 511.

Who to call

  • Live traffic and closures: FL511, or dial 511
  • Beeline Highway project: FDOT project manager Jessica Lewis, 561-370-1113; community outreach, Silvana Ojeda, 561-905-0167
  • I-95 at Northlake project: FDOT community outreach, Meredith Cruz, 561-589-9584
  • City road and bike lane projects: Palm Beach Gardens Engineering, 561-804-7012
  • All FDOT work in the county: District 4 Palm Beach County projects

Closures this week and next

From FDOT’s weekly traffic report for Nov. 6 to Nov. 13 and the city’s traffic alerts. Plans can change with weather; confirm on FL511 before you drive.

  • Veterans Day, Wednesday, Nov. 11: FDOT has scheduled no lane closures on the Beeline Highway or Earman River bridge jobs for the holiday.

  • Beeline Highway at Jog Road, overnight: from 8 p.m. to 6 a.m., Sunday through Thursday nights, through Thursday, Nov. 19, through traffic and left turns are closed at the intersection, so drivers may only turn right. The city’s alert for Nov. 10 to 13 says a detour is in place. FDOT’s report says drivers who want to go straight or left should turn right, make a U-turn and come back through the intersection.

  • Northlake Boulevard on both sides of Beeline Highway: one lane closed in each direction as needed, 10:30 a.m. to 6 p.m. weekdays. U-turns are not allowed at the intersection, and the Beeline ramp to eastbound Northlake stays closed until winter; turn right at the light instead.
  • Florida’s Turnpike at the Beeline Highway overpass: one lane closed in each direction Sunday night 10 p.m. to 6 a.m. and Monday through Thursday nights 9 p.m. to 5 a.m., through November. Southbound Turnpike lanes at the overpass are shifted to the inside.
  • Beeline Highway, Jog Road to the Turnpike overpass: one inside lane closed in each direction, 7 a.m. to 5 p.m. weekdays. The city says this runs through Friday, Nov. 13.
  • Beeline Highway, Blue Heron Boulevard to Northlake Boulevard, and Military Trail to Blue Heron: one lane closed in each direction, 7 a.m. to 6 p.m. weekdays.
  • Beeline Highway at Northlake Boulevard: one lane closed in each direction, 10 a.m. to 5 p.m. weekdays. Northwest-bound Beeline lanes from Military Trail to the Turnpike overpass stay shifted until summer 2027.
  • Beeline Highway at Jog Road: one lane closed in each direction, 10 a.m. to 6 p.m. weekdays. At Haverhill Road: 7 a.m. to 6 p.m. weekdays.
  • Beeline Highway left turn to eastbound Blue Heron Boulevard: closed around the clock through spring 2027. Detour: continue southeast on Beeline, north on Military Trail and east on Blue Heron. Eastbound Blue Heron from Beeline to Military Trail also loses its outside lane 7 a.m. to 6 p.m. weekdays.
  • U.S. 1 over the Earman River (North Palm Beach, about seven miles east): southbound traffic runs on the new southbound bridge and northbound traffic is shifted to the inside lanes. The outside lane from Anchorage Drive to Northlake closes intermittently 9:30 a.m. to 5 p.m. daily. FDOT gives summer 2027 for completion.
  • U.S. 1 from 59th Street to Northlake Boulevard (Riviera Beach, Lake Park and North Palm Beach): the center left-turn lane between Silver Beach Road and East Kalmia Drive is now permanently closed for a new raised median; drivers turn at the nearest signal. The northbound sidewalk from Access Road to West 11th Street is closed through December. This week one lane in each direction can close 9 p.m. to 7 a.m. Wednesday and Thursday nights, and 8 a.m. to 4:30 p.m. Thursday, Nov. 12, through Saturday, Nov. 14.
  • Flooded streets: after the early November rain, the city said 94% of its roads were clear as of 2:25 p.m. Wednesday, Nov. 4. Check a street on the city’s live flood map and never drive through standing water. Report a flooded road through the city’s Request Tracker.

Coming up

  • I-95 at Northlake Boulevard: FDOT expects to start its $54 million interchange project Friday, Nov. 13. Lane closures can run Sunday night through Saturday, 7 p.m. to 7 a.m. on I-95 and 9 p.m. to 7 a.m. on the I-95 ramps and Northlake, FDOT’s project flyer (PDF) says. FDOT holds an open house from 6 to 7 p.m. Thursday, Nov. 12, in the City Hall Council Chambers, 10500 N. Military Trail. The city’s meeting notice calls it a chance to hear the scope, timeline and traffic impacts. More in our story on the I-95 and Northlake work.
  • Gardens Parkway bike lanes and sidewalk: the city is taking bids until 3 p.m. Friday, Dec. 18, to add a 5-foot bike lane on both sides of Gardens Parkway between Alternate A1A and Prosperity Farms Road, and an 8-foot sidewalk on the south side from Fairchild Gardens Avenue to Prosperity Farms Road, its legal notice says. It is an FDOT Local Agency Program project. No start date has been set.

State projects (FDOT)

Project Where What Timeline
S.R. 710/Beeline Highway reconstruction Beeline Highway from Northlake Boulevard to Blue Heron Boulevard, plus the Turnpike bridge over Beeline Widening from four lanes to six, a new Turnpike bridge, a partial continuous flow intersection at Northlake, sidewalks and bike lanes Began March 18, 2024; finish late 2029; $148.2 million
I-95 interchange at Northlake Boulevard I-95 from south of Northlake to south of PGA Boulevard; Northlake from Military Trail to Silverthorne Drive Repaving, wider exit ramps, wrong-way driver detection, a fourth through lane on Northlake under I-95, more turn lanes and bike lanes Due to start Nov. 13, 2026; finish late 2029; $54 million; contractor OHLA-USA

On the Beeline job, FDOT says lane closures on Beeline, Northlake, Jog Road and Blue Heron take place daily and nightly as needed. One lane of the Turnpike may close from 10 p.m. to 6 a.m. Sunday nights and 8 p.m. to 6 a.m. Monday through Thursday nights, and the Turnpike ramps at Beeline may close overnight. FDOT’s October progress update (PDF) has the latest phase: FDOT’s November update (PDF) says the Beeline job was 52.6% complete on Nov. 2, and Turnpike bridge beams are due to go up from Nov. 30. FDOT’s project page now gives late 2029 for completion, matching its weekly report; it earlier said summer 2028.

Northlake Boulevard itself is a county road; Palm Beach County controls its lanes, speed limits and signals, the city’s Western Northlake traffic page explains. The Beeline intersection is outside the city limits.

City projects

  • Burns Road protected bike track: open. The 9.5-foot two-way bicycle track on the south side of Burns Road, from Military Trail to Alternate A1A, is complete and opened to the public in October, the city’s project page says. A 6-inch concrete curb separates it from traffic. The city calls it the first two-way protected bike lane in Palm Beach County. It cost $1,433,502.81: $1,302,181 from a Palm Beach County Metropolitan Planning Organization and FDOT grant and $131,321.81 from the city’s Mobility Impact Fund.
  • Fairchild Avenue. A 5-foot buffered bike lane on the north side, a 10-foot shared-use path on the south side, resurfacing and new landscaping. Work began in May 2026 and is due to finish in January 2027, according to the project page. Contact: Deputy City Engineer Giles Rhoads, 561-804-7013.
  • Coconut Boulevard extension. The city says a four-lane extension of Coconut Boulevard from Northlake to the Beeline has gone out to bid and is expected to be finished within two years of that notice.

Get alerts

Sign up for the city’s traffic alerts through Notify Me, and FDOT’s weekly lane closure report on its Palm Beach County page.

What this means for you

  • Driving Beeline at Jog Road after 8 p.m. Sunday to Thursday? Until Nov. 19 you can only turn right; plan another way to go straight or left.
  • Driving I-95 or Northlake at night from Friday, Nov. 13? Expect lane closures between Northlake and PGA Boulevard after 7 p.m. on I-95 and after 9 p.m. on the ramps and Northlake.
  • Heading to eastbound Blue Heron from Beeline? Use Military Trail until spring 2027.
  • Expect Beeline and Northlake slowdowns on the western side of the city until late 2029.
  • Questions about the I-95 job? FDOT’s open house is 6 to 7 p.m. Thursday, Nov. 12, at City Hall.
  • Check FL511 before you leave.

Related: getting around Palm Beach Gardens, building permits and zoning and who to call at City Hall.

Frequently asked questions

Can I turn left at Beeline Highway and Jog Road at night?

No. From 8 p.m. to 6 a.m., Sunday through Thursday nights, through Thursday, Nov. 19, through traffic and left turns are closed at the Beeline Highway and Jog Road intersection, FDOT says. Drivers turn right, make a U-turn and come back through the intersection.

When will the Beeline Highway construction be finished?

FDOT now gives late 2029 for the $148.2 million widening of Beeline Highway from Northlake Boulevard to Blue Heron Boulevard, on both its project page and its weekly traffic report. Work began March 18, 2024.

What is happening at I-95 and Northlake Boulevard?

FDOT expects to start its $54 million interchange project Friday, Nov. 13, widening the exit ramps and adding a fourth through lane on Northlake under I-95. Lane closures run overnight: 7 p.m. to 7 a.m. on I-95 and 9 p.m. to 7 a.m. on the ramps and Northlake. Completion is set for late 2029. An open house is 6 to 7 p.m. Thursday, Nov. 12, at City Hall.

Is the Burns Road bike lane open?

Yes. The city says the two-way protected bicycle track on the south side of Burns Road, from Military Trail to Alternate A1A, is complete and opened to the public in October 2026.